Asphalt Plant Locations

AT A GLANCE

  • Project Name: Dulles Toll Road Pavement Repairs
  • Location: 11750 Sunrise Valley Drive Reston, Virginia 20191
  • Duration: 4 months
  • Project Type: Civil ConstructionPublicRoadways
  • Status: Complete

Dulles Toll Road Pavement Repairs

This $2.8 Million rehabilitation project involved completing substantial amounts of work under tight deadline to reduce impact on this heavily travelled roadway.

Teams performed demolition of existing asphalt roadway, installation of 10” Portland Cement concrete pavement, and extensive full-depth patching. The project also required a 2” milling and overlay of existing asphalt surface, followed by thermoplastic striping, as well as installation of snow-plowable raised pavement markers and surface- mounted delineators. Virginia Paving also performed surface rideability testing to ensure quality of product.